KERC Transmission Tariff Regulations, 2006
[clause 2.3]
[clause 3.6.1]
b. Switchgear, including cable connections - 25 years
c. Underground Cable Including joint boxes and disconnected boxes - 35 years
d. Lines on fabricated steel supports operating at nominal voltages higher than 66 kV - 35 years
[appendix 2]
b. Admn. & General Expenses
c. Interest & Finance Charges
d. Return on Equity
e. Depreciation
f. Non-tariff income
g. Operation & Maintenance expenses
[clause 2.5.3]
b. Taxes on Income
[clause 2.5.3]
a. The approved aggregate gain or loss to the Licensee on account of uncontrollable factors and the mechanism by which the Licensee shall pass through such gains or losses
b. The approved aggregate gain or loss to the Licensee on account of Controllable factors and the mechanism to share such gains or losses
[clause 2.7.6]
2. O&M expenses (Rs. in lakh per bay) for year 2007-08, 2008-09 and 2009-10 are Rs. 31.63, Rs. 32.90 and Rs. 34.22 respectively.
[clause 3.11.3]
2. Payment of transmission charges below the target availability shall be on pro rata basis.
3. The transmission charges shall be calculated on monthly basis.
[clause 3.16]
TR = Net ARR/(12xTCC)
Where, TR: Transmission Rate in Rs./kW/month Net ARR: Net ARR, as determined.
TCC: Total Contracted Capacity in kW of the Transmission system by all Long-Term open access customers.
2. For short term open access customers the transmission charges shall be as follows:
2.1. Short Term Rate [ST rate] per day = 0.25* [Transmission expenditure /Annual peak]/365
2.2. Upto 6 hrs in a day in one block=0.25 * ST rate
2.3. More than 6 Hrs and upto 12 hrs in a day in one block= 0.50 * ST rate
2.4. More than 12 Hrs and upto 24 hrs in a day in one block= ST rate
[clause 3.15]
2. In case the actual transmission loss exceeds the normative loss level approved by the Commission, such excess loss shall be to the account of the Transmission Licensee and the Transmission Licensee shall compensate the Users at the weighted average cost of power purchase in that Financial year.
3. In case the actual transmission loss is less than the approved loss level, such savings shall be shared between the Transmission Licensee and the Users in the ratio of 70:30 during the first Control Period and in the ratio as may be decided by the Commission in the subsequent Control periods.
[clause 3.4]
Incentive = Annual Transmission Charges x [Annual availability achieved - Target Availability] / Target Availability;
Provided that no incentive shall be payable above the availability of 99.75%. (2) 50% of the Incentive shall be shared by the long-term customers in the ratio of their average allotted transmission capacity for the year.
[clause 3.17]
b. dated May 18, 2016
[clause 2.3]
[clause 2, subclause 3.11.2 and 3.11.3]
Short term (ST) rate per day / kW = 0.25 (net ARR / TCC) / 365
TCC = Total Contracted Capacity in kW of the Transmission system by all Long-Term Open access customers.
Net ARR : Net ARR as determined.
2. For short term open access customers the transmission charges shall be as follows:
2.1. Upto 6 Hrs in day in one block: 0.25 * ST Rate
2.2. More than 6 Hrs and upto 12 Hrs in day in one block: 0.50 * ST rate
More than 12 Hrs and upto 24 Hrs in a day in one block. : Equal to ST rate
[clause 2, subclause 3.15.1]
2. In case the actual transmission loss exceeds the normative loss level approved by the Commission,such excess loss shall be to the account of
Transmission Licensee and the Transmission Licensee shall be liable for penalty at the rate of 1% of the allowable RoE for every 0.5% variation in actual transmission loss over the approved range of transmission losses for the relevant period. Provided that if the actual transmission loss falls within the approved band, the
transmission licensee shall not be levied penalty or allowed any incentive.
3. In case the actual transmission loss is less than the approved loss level, such savings shall be shared between the Transmission Licensee and the Distribution licensee in the ratio of 50:50or in the ratio as may be decided by the Commission from time to time. Provided that the savings shall be computed at the rate of 1% of the allowable RoE for every 0.5% reduction in actual transmission loss below the lowerlimit of approved range of transmission loss for the relevant period.
[clause2, subclause 3.4]