Model RfP 2006
Resolution By
MoP
Effective Date
To be specified by the BPC
Validity of Bid
The bid shall remain valid for upto 180 days from the bid deadline
Submission method
Registered post, speed post, courier or by hand delivery to the specified BPC address. Telex/Fax/email/telegram shall not be considered
Contract Performance Guarantee
CPG would be computed on the basis of ₹6 lakh/km for the total tx line length which shall be provided separately to each of the LT tx customer calculated in the ratio of the allocated project capacity [clause 2.21]
Bid Bond
Computed on the basis of ₹3 lakh/km for all lines [clause 2.20]
Bid evaluation
The bid evaluation will consist of responsiveness check, evaluation of financial bids and bidder selection [clause 3]
Corrigendum/ Amendment, if any
Yes
Amendment 1
Resolution By
MoP
Amendment 2
Resolution By
MoP
Contract Performance Guarantee
Bidders are required to quote tx charges for a period of 35 years from SCOD of the project [clause 2.14.1.2 e]
Bid evaluation
tx charges will be levelised over a period from the SCOD up to 35 years [clause 3.3.2.2]
Amendment 3
Resolution By
MoP
Contract Performance Guarantee
CPG would be computed on the basis of ₹9 lakh/km for the total tx line length and ₹0.75 lakh/MVA for substations
Bid Bond
Computed on the basis of ₹3.5 lakh/km for total tx line length and ₹0.3 lakh/MVA for substations